Stages
The construction of a loft takes approximately 6 weeks.
Here we have broken down a typical build into stages.
Before any building works can start, permission from the local authority
must be obtained.
Week 1 Scaffolding is erected
Opening made in roof
Steel installed
Week 2
Build floor
Dormer construction
Velux frames constructed